Well Details

Well ID: 34-013-20979
Loading map...
Country: United States
State: Ohio
County: Belmont
Municipality: Wayne Township
Operator Name: GULFPORT APPALACHIA LLC
Well Pad ID: US-OH-001317
Farm/Lease Name: WARRICK 210463
License Status: Producing
License Date: 2015-09-30
Spud Date: 2015-12-01
Spud Drilling Contractor: NOMAC DRILLING CORP
Final Drill Date: 2015-12-30
Well Total Depth: 17322.00 ft
Configuration: Horizontal
Latitude: 39.940000
Longitude: -81.110000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2015-09-30 Proposed Formations:UTICA THRU POINT PLEASANT, Issued Date:9/30/2015, Expired Date:9/29/2017 12:00:00 PM, Drilling unit acres:199.701, Proposed Well Type:OG, Proposed Well Class:POOL
Reached Total Depth 2015-12-30
Correction to Well 2016-05-27 CHANGE IN TARGET/TAKEPOINT/ACREAGE AS-DRILLED PLAT-ALE
Completion Report Received 2016-12-16
Construction Permit Expires 2017-09-29
Record Last Modified 2017-10-23

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2016-12-20 9570 17180 0
9570 17180 0
9570 17180 0

For data sources see[3]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 06/25/2016 07/14/2016 9041 8,848,850.0 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Sand (40/70 Proppant) Taylor Frac Proppant Silica Substrate 14808-60-7 100 9.37624 8,668,480.0
Hydrochloric Acid (28%) Oxy Acidizing Hydrochloric Acid (Hydrogen Chloride) 7732-18-5 36 0.0579141 53542.5
Water 7732-18-5 64 0.102958 95186.7
Water Gulfport Energy Corporation Carrier/Base Fluid Water 7732-18-5 100 89.272 82,533,400.0
X-CHEM SC-82 X-Chem, LLC Scale Inhibitor Sodium polyphosphonate Proprietary 30 0.00426397 3942.11
Hydrochloric Acid 7647-01-0 3 0.000426397 394.211
Mathanol 67-56-1 1 0.000142132 131.404
Water 7732-18-5 66 0.00938074 8672.65
NEFE-180 Chemplex Corrosion Inhibitor/Iron Control 2-Ethylhexanol 104-76-7 10 0.000100084 92.529
Olefin Proprietary 5 0.00005004 46.265
2-Propyn-1-ol 107-19-7 5 0.00005004 0
Methanol 67-56-1 35 0.000350294 323.853
Fatty acids, tall oil 61790-12-3 5 0.00005004 46.265
Alcohols, C14-15, ethoxylated 68951-67-7 5 0.00005004 46.265
Coconut oil acid diethanolamine 68603-42-9 5 0.00005004 46.265
Acetic acid 64-19-7 65 0.000650547 601.441
FRA-409 Lubrizol Friction Reducer Copolymer of 2-propenamide Proprietary 30 0.0233206 21560.3
Ammonium Chloride 12125-02-9 1 0.000777353 718.676
Distillates (Petroleum), Hydrotreated Light 64742-47-8 20 0.0155471 14373.5
Alkanolamide 93-83-4 2 0.00155471 1437.35
Alcohols, C12-16, Ethoxylated 68551-12-2 2 0.00155471 1437.35
X-CHEM B-84 X-Chem, LLC Biocide Didecyl dimethyl ammonium chloride 7173-51-5 8 0.00270063 2496.78
n-Alkyl dimethyl benzyl ammonium chloride 68424-85-1 5.5 0.00185668 1716.53
Ethanol 64-17-5 4 0.00135032 1248.39
Water 7732-18-5 55.5 0.0187356 17321.4
Glutaraldehyde 111-30-8 27 0.00911463 8426.62
Sand (100 Mesh Proppant) Taylor Frac Proppant Silica Substrate 14808-60-7 100 1.06419 983860

For data sources see[4]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
2016-07-14 H2O 15 186060 Gal 225320 STINGRAY PRESSURE PUMPING LLC STAGE 43/43

50 SHOTS

H2O 0 0 Gal 0
2016-06-25 H2O 15 367626 Gal 228340 STINGRAY PRESSURE PUMPING LLC STAGE 1/43

50 SHOTS

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2016 GULFPORT ENERGY CORPORATION 2151916 0 133
2017 GULFPORT ENERGY CORPORATION 3477473 3 355
2018 GULFPORT ENERGY CORPORATION 1640218 0 363
2019 GULFPORT ENERGY CORPORATION 276632 0 90

For data sources see[6] [7]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2016 GULFPORT ENERGY CORPORATION Brine 9338 133
2017 GULFPORT ENERGY CORPORATION Brine 42192 355
2018 GULFPORT ENERGY CORPORATION Brine 7055 363
2019 GULFPORT ENERGY CORPORATION Brine 863 90

For data sources see[8] [9]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1262618210 2015-12-29 0:00 DD No Violations 2.50
-1894460387 2016-10-5 0:00: PW No Violations 1.00
-2099945626 2015-12-16 0:00 CS No Violations
-637307109 2015-12-17 0:00 DD No Violations 3.00
-957129881 2018-6-14 0:00: PW No Violations 0.50
0109402830 2015-12-15 Drill / Deepen / Reopen No Violations My inspection today finds the rig lost circulation on the well at a depth of 8471 after drilling thirty feet below the casing shoe. The rig is mixing a 100 barrel 100 pound lost circulation material pill. If they cannot reestablish circulation they will attempt to cement at the base of the 9.625 casing shoe.
0637307109 2015-12-17 Drill / Deepen / Reopen No Violations My inspection today finds the drilling rig is preparing to set down on the cement retainer set tool for a second attempt to fish it out of the hole. The retainer tool is at a depth of 8341.
0666642135 2015-12-21 Drill / Deepen / Reopen No Violations My inspection today finds the drilling contractor, Nomac 83, is preparing to install a whipstock in the 9.625 casing at 8154. They will then mill through the casing and resume drilling.
0724073968 2016-01-04 Drill / Deepen / Reopen No Violations On this day the process of rigging down Nomac Rig # 83 was underway. Once the rig down process is complete this rig will transit to the George pad.
0957129881 2018-06-14 Production Wells No Violations On the day of my inspection I witnessed that the well was equipped with 5.5 inch diameter production casing that was open flowing. Annular pressure monitoring was in place, the intermediate casing gauge read 1000 pounds per square inch, the surface casing gauge read 0 pounds per square inch. Production equipment included a Sand Separator, Gas Processing unit and 4- 400 barrel purge tanks, and a 50 barrel produced water tank shared with 34013209710000, 34013209720000, 34013209730000. Identification tags were present, and production was up to date. No violations were found at the time of my inspection.
109402830 2015-12-15 0:00 DD No Violations 3.00
1262618210 2015-12-29 Drill / Deepen / Reopen No Violations My inspection today finds Nomac rig 83 is drilling an 8.5 borehole at a depth of 16,751. Evolution Energy Trucking is on site removing accumulated rain water from the containment.
1268197136 2018-08-01 Production Wells No Violations Status check inspection found the well pad surface and lease road of stone construction, the lease road does have identification posted and a gate present. As you enter the well pad there is a Mark West midstream station on the left side. Situated in the center of the well pad is 4 producing wells all equipped with emergency shut down devices on the production tree outlet side past the 2 primary master valves, the production flow line pressure is 500 pounds per square inch (psi). The 5.5 production casing internal pressure is 500 psi. The well head A &B sections is equipped with valves and riser pipes with gauges present to monitor annular pressure. The A section riser pipe which gauges the pressure between the 13.375 and 9.625 diameter casing strings showed 10 pounds pressure. The B section which is the pressure between the 9.625 and 5.5 diameter casing strings has 650 pressure showing on the gauge. The wells are selling into gas processing units with a total of 4 units present on location. At the front left hand corner of the well pad is the production facility consisting of 4 steel construction 400 barrel production tanks situated inside a polymer lined steel containment dike area. Fire extinguishers and emergency shut down control points are situated on the pad at all critical areas. Proper well identification is posted at each well along with hazard identification on each production tank. The well pad earthen berm is in good repair and the perimeter area of the well pad has vegetation established.
1681997505 2015-12-18 Drill / Deepen / Reopen No Violations I spoke to Nick Sharp, Gulfport Drilling Consultant, about the well. Mr. Sharp stated that a caliper log was performed and indicated that the casing was parted at three joints from bottom. He said that the company would notify the Division once a plan to remediate was developed.
1894460387 2016-10-05 Production Wells No Violations Completion efforts on this pad are finished. Production crews are on this site assembling the production equipment. Once production equipment is finalized the wells are anticipated to begin producing.
2099945626 2015-12-16 Casing String Witnessed No Violations My inspection today finds the drilling rig, Nomac 83, drilled 1150 of 17.5 borehole. The rig then ran 1147 of 13.375 casing. Stingray Cementing cemented the casing by circulating 1030 sks of class H cement around the backside of the casing. I witnessed thirty barrels of cement circulate to surface.
666642135 2015-12-21 0:00 DD No Violations 2.00
724073968 2016-1-4 0:00:0 DD No Violations 1.00
862805597 2020-2-14 0:00: PW No Violations 0.20

For data sources see[10]

References