X

Track changes made to this page

If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.



Privacy policy
Close this window

powered by ChangeDetection

0554141105002

Well Details

Well ID: 0554141105002
Loading map...
Location: 00/05-11-055-14W4/2
Location Alias: 00/05-11-55-14 W4M
Location Alias 2: 00/05-11-055-14 W4/02
Country: Canada
Province: Alberta
Township: 055
Meridian: 4
Range: 14
Section: 11
County/Municipality: County of Two Hills No. 21
Well Name: CPG HAIRY 5-11-55-14
Operator Name: Crescent Point Energy Corp.
License Number: 0003829
License Date: 1951-11-22
License Status: Abandoned
Spud Date: 1951-12-02
Final Drill Date: 1952-01-12
Well Total Depth: 998.20 m
Surface Hole Latitude: 53.734998
Surface Hole Longitude: -111.981754

For data sources see[1][2]

Well History

Date Event
1909-09-09 Well Log Performed
1951-11-22 Obtained License
1951-12-02 Lost Circulation Occurred
1951-12-12 Drill Stem Test Performed
1951-12-17 Drill Stem Test Performed
1951-12-25 Production Casing Operation Performed
1952-01-04 Drill Stem Test Performed
1952-01-07 Drill Stem Test Performed
1952-01-11 Drill Stem Test Performed
1952-01-12 Drill Stem Test Performed
1952-01-12 Finished Drilling
1952-01-12 Well Mode changed to Drilled and Cased
1965-03-25 Perforation Treatment Performed - Bullet Perforation
1965-03-26 Perforation Treatment Performed - Bridge Plug Capped W/Cement
1965-03-26 Perforation Treatment Performed - Bullet Perforation
1978-02-03 Perforation Treatment Performed - Jet Perforation
1978-02-05 Well Began Production
1978-02-05 Well Fluid changed to Gas
1978-02-05 Well Mode changed to Flowing
1981-11-04 Perforation Treatment Performed - Acid Squeeze - Press Used
1999-08-01 Well Fluid changed to Gas
1999-08-01 Well Mode changed to Suspended
2001-03-11 Perforation Treatment Performed - Bridge Plug Capped W/Cement
2001-03-11 Perforation Treatment Performed - Jet Perforation
2001-03-11 Plug Back Performed
2001-03-11 Well Fluid changed to Gas
2001-03-11 Well Log Performed
2001-03-11 Well Mode changed to Suspended
2001-03-12 Perforation Treatment Performed - Bridge Plug Capped W/Cement
2001-03-12 Perforation Treatment Performed - Remedial Casing
2001-03-12 Plug Back Performed
2001-03-12 Well Fluid changed to Gas
2001-03-12 Well Mode changed to Abandoned Zone
2002-11-28 Perforation Treatment Performed - Jet Perforation
2002-11-30 Perforation Treatment Performed - Jet Perforation
2002-12-03 Perforation Treatment Performed - Acid Squeeze - Press Used
2002-12-05 Perforation Treatment Performed - Remedial Casing
2008-11-19 Well Log Performed
2008-11-20 Perforation Treatment Performed - Jet Perforation
2008-11-20 Well Log Performed
2008-11-21 Perforation Treatment Performed - Abrasa-Jet Perforation
2008-11-22 Perforation Treatment Performed - Remedial Casing
2008-11-25 Perforation Treatment Performed - Jet Perforation
2008-11-25 Well Log Performed
2008-11-26 Perforation Treatment Performed - Remedial Casing
2008-11-28 Perforation Treatment Performed - Cement Plug
2008-11-28 Plug Back Performed
2009-01-15 Well Abandoned
2009-01-15 Well Fluid changed to Gas
2009-01-15 Well Mode changed to Abandoned

For data sources see[3]


Perforation Treatments

Perforation Date Perforation Type Interval Top (m) Interval Base (m) Number of Shots
1965-03-25 Bullet Perforation 635.80 636.70 7
2002-11-28 Perforation 347.00 347.90 99
2002-11-28 Perforation 357.00 357.90 99
2002-11-30 Perforation 349.00 349.90 99
2002-12-03 Acid Treatment 349.00 357.90 0
2002-12-05 Remedial Casing Cementing 347.00 357.90 0
2008-11-20 Perforation 487.70 488.70 13
2008-11-20 Perforation 390.10 391.10 13
2008-11-21 Hydra Jet Perforation 356.00 360.00 13
2008-11-22 Remedial Casing Cementing 487.70 488.70 0
2008-11-22 Remedial Casing Cementing 390.10 391.10 0
1965-03-26 Packing Device Capped w/Cement 609.60 609.60 0
2008-11-22 Remedial Casing Cementing 356.00 360.00 0
2008-11-25 Perforation 322.50 323.50 13
2008-11-25 Perforation 273.00 274.00 13
2008-11-25 Perforation 204.90 205.90 13
2008-11-26 Remedial Casing Cementing 322.50 323.50 0
2008-11-26 Remedial Casing Cementing 273.00 274.00 0
2008-11-26 Remedial Casing Cementing 204.90 205.90 0
2008-11-28 Cement Plug 159.10 507.00 0
1965-03-26 Bullet Perforation 527.90 528.80 7
1978-02-03 Perforation 487.10 489.20 7
1981-11-04 Acid Treatment 487.10 489.20 0
2001-03-11 Packing Device Capped w/Cement 514.00 522.00 0
2001-03-11 Perforation 357.00 357.60 72
2001-03-12 Remedial Casing Cementing 357.00 357.60 0
2001-03-12 Packing Device Capped w/Cement 471.00 479.00 0

For data sources see[4]


Production Data

Period Total Production Hours Gas Quantity (m3) Oil Quantity (m3) Water Quantity (m3)
1978 6898 0.0 0.0 0.0
1979 7683 0.0 0.0 0.0
1980 5050 0.0 0.0 0.0
1981 8417 0.0 0.0 0.0
1982 5623 0.0 0.0 0.0
1983 7469 0.0 0.0 0.0
1984 8495 0.0 0.0 0.0
1985 4487 0.0 0.0 0.0
1986 8710 0.0 0.0 0.0
1987 5611 0.0 0.0 0.0
1988 5439 0.0 0.0 0.0
1989 3200 0.0 0.0 0.0
1990 2738 0.0 0.0 0.0
1991 2881 0.0 0.0 0.0
1992 3236 0.0 0.0 0.0
1994 3647 0.0 0.0 0.0

For data sources see[5]

Occurences

Occurence Date Occurence Type Occurence Depth (m) Occurence Control Depth (m)
1951-12-02 Lost Circulation 627.90 637.00

For data sources see[6]

References