Well Details

Well ID: 0174100311000
Loading map...
Location: 00/11-03-017-10W4/0
Location Alias: 00/11-03-17-10 W4M
Location Alias 2: 00/11-03-017-10 W4/00
Country: Canada
Province: Alberta
Township: 017
Meridian: 4
Range: 10
Section: 03
County/Municipality: Cypress County
Well Name: PINE CLIFF ALDSON 11-3-17-10
Operator Name: Pine Cliff Energy Ltd.
License Number: 0046413
License Date: 1973-07-05
License Status: Issued
Spud Date: 1973-07-25
Final Drill Date: 1973-07-26
Well Total Depth: 442.00 m
Surface Hole Latitude: 50.408178
Surface Hole Longitude: -111.304510

For data sources see[1][2]

Well History

Date Event
1909-09-09 Well Log Performed
1973-07-05 Obtained License
1973-07-26 Finished Drilling
1973-07-27 Production Casing Operation Performed
1973-08-02 Perforation Treatment Performed - Bullet Perforation
1973-08-02 Perforation Treatment Performed - Selective Bullet Perforations
1973-08-20 Perforation Treatment Performed - Fractured
1973-08-24 Perforation Treatment Performed - Bullet Perforation
1973-08-24 Perforation Treatment Performed - Fractured
1973-08-24 Perforation Treatment Performed - Selective Bullet Perforations
1974-02-22 Well Mode changed to Drilled and Cased
1975-03-20 Well Began Production
1975-03-20 Well Fluid changed to Gas
1975-03-20 Well Mode changed to Flowing

For data sources see[3]


Perforation Treatments

Perforation Date Perforation Type Interval Top (m) Interval Base (m) Number of Shots
1973-08-02 Bullet Perforation 337.10 337.70 7
1973-08-24 Bullet Perforation 341.70 342.30 7
1973-08-24 Bullet Perforation 345.00 345.60 7
1973-08-24 Bullet Perforation 352.70 353.30 7
1973-08-24 Selective Bullet Perforations 355.10 355.10 3
1973-08-24 Bullet Perforation 358.10 358.70 7
1973-08-24 Bullet Perforation 363.60 364.20 7
1973-08-24 Fracture 337.10 364.20 0
1973-08-02 Bullet Perforation 341.70 342.30 7
1973-08-02 Bullet Perforation 345.00 345.60 7
1973-08-02 Bullet Perforation 352.70 353.30 7
1973-08-02 Selective Bullet Perforations 355.10 355.10 3
1973-08-02 Bullet Perforation 358.10 358.70 7
1973-08-02 Bullet Perforation 363.60 364.20 7
1973-08-20 Fracture 337.10 364.20 0
1973-08-24 Bullet Perforation 337.10 337.70 7

For data sources see[4]


Production Data

Period Total Production Hours Gas Quantity (m3) Oil Quantity (m3) Water Quantity (m3)
1975 6462 0.0 0.0 0.0
1976 8427 0.0 0.0 0.0
1977 8431 0.0 0.0 0.0
1978 7627 0.0 0.0 0.0
1979 7851 0.0 0.0 0.0
1980 8380 0.0 0.0 0.0
1981 3688 0.0 0.0 0.0
1982 7111 0.0 0.0 0.0
1983 7435 0.0 0.0 0.0
1984 1223 0.0 0.0 0.0
1985 2177 0.0 0.0 0.0
1986 1610 0.0 0.0 0.0
1987 2365 0.0 0.0 0.0
1988 7325 0.0 0.0 0.0
1989 7100 0.0 0.0 0.0
1990 7664 0.0 0.0 0.0
1991 6162 0.0 0.0 0.0
1992 8783 0.0 0.0 0.0
1993 8747 0.0 0.0 0.0
1994 8755 0.0 0.0 0.0
1995 8759 0.0 0.0 0.0
1996 8783 0.0 0.0 0.0
1997 8759 0.0 0.0 0.0
1998 8759 0.0 0.0 0.0
1999 8759 0.0 0.0 0.0
2000 8595 0.0 0.0 0.0
2001 8493 0.0 0.0 0.0
2002 8716 0.0 0.0 0.0
2003 8678 0.0 0.0 0.0
2004 8662 0.0 0.0 0.0
2005 8753 0.0 0.0 0.0
2006 5798 0.0 0.0 0.0
2007 8759 0.0 0.0 0.0
2008 8783 0.0 0.0 0.0
2009 8759 0.0 0.0 0.0
2010 8015 0.0 0.0 0.0
2011 8759 0.0 0.0 0.0
2012 8783 0.0 0.0 0.0
2013 8711 0.0 0.0 0.0
2014 8711 0.0 0.0 0.0
2015 7535 0.0 0.0 0.0
2016 7319 0.0 0.0 0.0
2017 72 0.0 0.0 0.0
2018 4368 0.0 0.0 0.0
2019 8759 0.0 0.0 0.0
2020 2183 0.0 0.0 0.0

For data sources see[5]