X

Track changes made to this page

If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.



Privacy policy
Close this window

powered by ChangeDetection

37-125-24303

Well Details

Well ID: 37-125-24303
Loading map...
County: Washington
Municipality: Robinson Township
Operator Name: CHEVRON APPALACHIA LLC
Well Pad ID: 147136
Farm/Lease Name: ROBINHILL 21H
First Permit Date: 2010-10-19
Last Permit Date: 2010-10-19
Spud Date: 2010-12-14
Unconventional: Yes
Horizontal: Yes
Producing: Yes
Violations: None
Latitude: 40.466861
Longitude: -80.351416

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID
1938168 2010-12-16 No Violations Noted Randsom - Well spud, site still under construction , E&S in place on main pad,
1944794 2010-11-16 No Violations Noted
1951144 2011-01-13 No Violations Noted On January 13th, 2011 I conducted an inspection of the above site. A portion of the fill side of the pad had sliped during construction. I met with Atlas representatives Gary Bowlen, Chad Eisenman, and Nick Staffieri on site. The fill side was still an estimated 14' below the proposed finished elevation. Multiple scarp faces were evident with a vetical separation of over 20' at the greatest. All material that moved stayed within the limit of disturbance. Some material had entered the interceptor channel at the base of the slope. No streams or watercourses are in close proximity to the base of the slope. The material that slid appeared dry and no springs or seeps were observed. The operator is to install additional E&S controls around the base of the slide and forward the reconstruction plan once designed.
1953092 2011-01-25 No Violations Noted On January 25th, 2011 I conducted a follow up inspection of the site in response to the slide and inspection on January 13th, 2011. Additioanl E&S controls were installed on the lower edge at the toe of the slip. During excavation and reconstruction the material began to move again. A scarp face of approximately 4' had developed. Constructed had halted until the engineers can evaluate the soil conditions and formualte a new plan for the excavation.
1957864 2011-02-04 No Violations Noted On February 4th, 2011 I conducted a follow up inspection of the site in response to the slide and inspection on January 13th and 25th, 2011. The lower side of the pad continues to slip during excavation. Construction efforts had been stopped. Temporary E&S controls put in place will remain in place until drilling is completed. After drilling is completed reclamation procedures are to start immediately, The rig was moving onsite today. A Site ID and E&S plan were posted onsite. The access road was in good condition. No spills/ leaks were observed at the time of inspection.


1958492 2011-02-09 No Violations Noted On February 9th, 2011 I conducted a follow up inspection of the site in response to the slide and inspections on January 13th and 25th, 2011. No new movement was observed. Construction efforts had been stopped. Temporary E&S controls put in place will remain in place until drilling is completed. After drilling is completed reclamation procedures are to start immediately. Drilling was started. A Site ID and E&S plan were posted onsite. The access road was in good condition. The pit appeared to be in good condition. No spills/ leaks were observed at the time of inspection.
1961856 2011-03-10 No Violations Noted On March 10th 2011 I conducted a routine inspection of the above site. Drilling was completed and the rig had moved offsite. The drill cuttings were being removed with an excavator and being hauled offsite. No additional movement was observed on the slide. The access road was in good condition. A site ID and E&S plan were posted on site. Excess runoff from the pad was beginning to crate a ditch and flow around the sediment trap. Some material upslope of the sediment trap had slid into the trap. Water flowing around the trap was undermining the filter sock and flowing into a wooded area approx 200¿. No streams or watercourses close. Crews were on site immediately to divert water into the sediment trap, a diversion was built at the top of the pad, and repairs and additions were made to the filter sock.
1961858 2011-03-11 No Violations Noted On March 11th 2011 I conducted a follow up inspection of the above site in response to the inspection on 3/10/2011. Straw bales had been added to the slope approaching the sediment trap to divert water into the trap. Straw bales had been added behind the filter sock below the sediment trap and repairs were made to the sediment trap. No more erosion was evident. All activities were within the limit of disturbance
1992019 2011-06-27 No Violations Noted On June 27th 2011 I conducted a routine inspection of the above site. Drilling was completed and production units were being installed. The pit was closed. The slide on the fill slope was not yet repaired awaiting restoration of the site. The access road was in good condition, Site ID and E&S plan were posted on site. No erosion was leaving site and was contained within the E&S controls. The operator should continue to monitor and inspection the E&S controls routinely and after each runoff event until site restoration is complete and permanent stabilization is established.
2083597 2012-07-12 No Violations Noted Looked at small slide on Robinhill #21. Small enough that they don't need a ESCPG-01. I will continue to monitor.
2085188 2012-07-20 No Violations Noted
2094821 2012-08-22 No Violations Noted On August 22, 2012, I stopped for a routine inspection at Chevron’s Robinhill #21; I met with Blake Loke, Matthew Barch and others.

Chevron is still planning on fixing this slide before the end of this growing season and is finalizing the plans. They have also talked to Robinson Township about permitting.

The slide itself appears unchanged since my last visit.

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS
2012-2 186975.0 184.0 232.8 184.0 0.0 0.0
2012-1 332414.0 182.0 1339.45 182.0 0.0 0.0
2011-2 43316.0 17.0 724.73 17.0 0.0 0.0
2011-1 0.0 0.0 0.0 0.0 0.0 0.0
2011-1 0.0 0.0 0.0 0.0 0.0 0.0
2010-2 0.0 0.0 0.0 0.0 0.0 0.0

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE
2012-2 PRODUCED FLUID 1744.0 Bbl INJECTION DISPOSAL WELL 34-121-23995 HUNTER DISPOSAL - WARREN DRILLING CO #1 (SWIW #6) DEXTER CITY OH
2011-1 DRILLING FLUID WASTE 8534.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PAR000519462 ADVANCED WASTE SERVICES OF PA (NEW CASTLE) NEW CASTLE PA
2011-1 FRACING FLUID WASTE 7820.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PAR000519462 ADVANCED WASTE SERVICES OF PA (NEW CASTLE) NEW CASTLE PA
2011-1 PRODUCED FLUID 1300.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PAR000519462 ADVANCED WASTE SERVICES OF PA (NEW CASTLE) NEW CASTLE PA
2011-1 FRACING FLUID WASTE 1035.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0253723 APPALACHIAN WATER SERVICES LLC (RONCO WTP) MASONTOWN PA
2011-1 DRILLING FLUID WASTE 100.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE 34-007-24355 B & B OILFIELD SERVICE - MILLER & CO #3 (SWIW #28) GARRETTSVILLE OH
2011-1 FRACING FLUID WASTE 4305.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE 34-007-24355 B & B OILFIELD SERVICE - MILLER & CO #3 (SWIW #28) GARRETTSVILLE OH
2011-1 PRODUCED FLUID 615.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE 34-007-24355 B & B OILFIELD SERVICE - MILLER & CO #3 (SWIW #28) GARRETTSVILLE OH
2011-1 DRILLING FLUID WASTE 440.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0101508 PA BRINE TRT INC - FRANKLIN PLT - VENANGO CO FRANKLIN PA
2011-1 FRACING FLUID WASTE 85.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095273 PA BRINE TRT INC - JOSEPHINE PLT, INDIANA COUNTY JOSEPHINE PA
2011-1 DRILLING FLUID WASTE 340.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0091472 TUNNELTON LIQUIDS COMPANY SALTSBURG PA
2011-1 FRACING FLUID WASTE 345.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0091472 TUNNELTON LIQUIDS COMPANY SALTSBURG PA
2011-1 PRODUCED FLUID 78.0 Bbl IDENTIFY METHOD IN COMMENTS 34-167-29359 WEST VIRGINIA OIL GATHERING
2011-2 PRODUCED FLUID 537.0 Bbl INJECTION DISPOSAL WELL 34-121-2-3995 HUNTERS SWIW #5 RENO OH
2012-1 PRODUCED FLUID 3621.0 Bbl INJECTION DISPOSAL WELL 34-121-23995 WARREN DRILLING CO #1 (SWIW #6) HUNTER DISPOSAL DEXTER CITY OH

References