37-063-36846

Well Details

Well ID: 37-063-36846
Loading map...
County: Indiana
Municipality: Brush Valley Township
Operator Name: CHEVRON APPALACHIA LLC
Well Pad ID: 148232
Farm/Lease Name: DICK 1H
First Permit Date: 2010-04-30
Last Permit Date: 2010-04-30
Spud Date: 2011-01-28
Unconventional: Yes
Horizontal: Yes
Well Status: ACTIVE
Violations: 0
Latitude: 40.499277
Longitude: -79.068333

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS
2010-3 0.0 0.0 0.0 0.0 0.0 0.0
2010-2 0.0 0.0 0.0 0.0 0.0 0.0
2010-2 0.0 0.0 0.0 0.0 0.0 0.0
2011-1 0.0 0.0 0.0 0.0 0.0 0.0
2011-2 0.0 0.0 0.0 0.0 0.0 0.0
2011-2 0.0 0.0 0.0 0.0 0.0 0.0
2012-1 0.0 0.0 0.0 0.0 0.0 0.0
2012-2 0.0 0.0 0.0 0.0 0.0 0.0
2013-1 0.0 0.0 0.0 0.0 0.0 0.0
2013-2 0.0 0.0 0.0 0.0 0.0 0.0
2014-1 0.0 0.0 0.0 0.0 0.0 0.0
2014-2 0.0 0.0 0.0 0.0 0.0 0.0
2015-02 0.0 0.0 0.0 0.0 0.0 0.0
2015-01 0.0 0.0 0.0 0.0 0.0 0.0
2015-03 0.0 0.0 0.0 0.0 0.0 0.0

For data sources see[1]

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE
2011-1 DRILL CUTTINGS 352.47 Tons LANDFILL 100172 ARDEN LANDFILL WASHINGTON PA

For data sources see[2]

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID VIOLATION CODE VIOLATION_COMMENT
1942800 2011-01-14 No Violations Noted Id sign ok. Site constructed. Location staked. No open pits. Site snow covered but no apparent problems.
1944402 2011-01-20 No Violations Noted Marcellus well. Conductor pipe set. Site ID sign in place. E&S plan on site. Setting up drilling equipment at time of inspection.

Approved ESCGP-1 permit on site. Technical review of ESCGP-1 completed.

Site and access road snow covered at time of inspection, although no obvious signs of accelerated erosion were found leaving access road or well site.  Appeared as though all BMP's were in place in accordance with E&S plan, and were properly maintained.  Minor E&S issue discussed with operator representative Matt Barch, and addressed through compliance assistance in technical inspection of ESCGP-1 plan.  No drill pit constructed on site (closed loop system to be utilized).  No frac pit constructed yet.  No violations found.
1944598 2011-01-19 No Violations Noted
1946175 2011-01-25 No Violations Noted
1947172 2011-01-28 No Violations Noted Marcellus well. Conductor pipe set. Site ID sign in place. E&S plan on site. Drilling rig in place.

Approved ESCGP-1 permit on site. Technical review of ESCGP-1 completed.

Site and access road snow covered at time of inspection, although no obvious signs of accelerated erosion were found leaving access road or well site.  Appeared as though all BMP's were in place in accordance with E&S plan, and were properly maintained.

No drill pit constructed on site (closed loop system to be utilized). No frac pit constructed yet. No violations found. No signs of any spills or discharges. No E&S issues found. No violations found.

1947871 2011-02-04 No Violations Noted
1947880 2011-02-02 No Violations Noted
1950400 2011-02-15 No Violations Noted Marcellus well. Site ID sign in place. E&S plan on site. BJ service company on site for cementing.

Approved ESCGP-1 permit on site. Technical review of ESCGP-1 completed.

Site and access road snow covered at time of inspection, although no obvious signs of accelerated erosion were found leaving access road or well site.  Appeared as though all BMP's were in place in accordance with E&S plan, and were properly maintained.

Drill cuttings and fluids being contained in above ground tanks (closed loop system being used). No frac pit constructed. No violations found. No signs of any spills or discharges. No E&S issues found. No violations found.

1953155 2011-02-24 No Violations Noted
1955295 2011-03-02 No Violations Noted Marcellus well. Site ID sign in place. E&S plan on site. Drilling taking place at time of inspection.

Approved ESCGP-1 permit on site. Technical review of ESCGP-1 completed. Drill cuttings and fluids being contained in above ground tanks (closed loop system being used). No frac pit constructed. Access road was stabilized with rock. Rock installed in all ditch lines, and culvert outlets. No signs of accelerated erosion on roadway. BMP's installed on site in accordance with E&S plan.

  • Some minor repairs are needed to the BMP's, in particular to the sediment trap on the far side of the site. This was discussed with on-site
   company representative Don Henson, as well as company rep Matt Barch.  Both indicated the concerns would be immediately 
   addressed. 
1956869 2011-03-09 No Violations Noted Marcellus well. Site ID sign in place. E&S plan on site. Drilling completed, currently drilling second well on same pad.

Approved ESCGP-1 permit on site. Technical review of ESCGP-1 completed. Access road was stabilized with rock. Rock installed in all ditch lines, and culvert outlets. No signs of accelerated erosion on roadway. BMP's installed on site in accordance with E&S plan, and adequately maintained. Site is stabilized with rock. Perimeter of site seeded/mulched, and erosion blankets installed. Minor repairs have been completed to the sediment trap on the far side of the site in response to compliance assistance inspection of 3/2/11. Site is in compliance. No E&S issues found. No violations found.

1965133 2011-03-25 No Violations Noted Marcellus well. Site ID sign in place. E&S plan on site. Drilling recently completed. Not equipped for production.

Approved ESCGP-1 permit on site. Technical review of ESCGP-1 completed. Access road was stabilized with rock. Rock installed in all ditch lines, and culvert outlets. No signs of accelerated erosion on roadway. BMP's installed on site in accordance with E&S plan, and adequately maintained. Site is stabilized with rock. Perimeter of site seeded/mulched, and erosion blankets installed. No impoundments/pits on site. No E&S issues found. No violations found. No ev idence of any spills or discharges.

1979929 2011-06-08 No Violations Noted
2047593 2012-03-02 No Violations Noted
2121806 2012-03-02 No Violations Noted
2126972 2012-12-06 No Violations Noted At the time of inspection, well sign, ES plan, and ESCGP-1 present. Access road stable. Well site gated. Multi well pad. Site is surrounding by wire fence in order to prevent third party access. Drilling completed 2/24/11. Pad adequately rocked. Wells drilled, not yet fraced nor equipped for production. Site is temporarily stabilized. No ES concerns noted. Operator has plans to permanently restore well site March 2013, a letter has been submitted discussing restoration efforts and timeline to Alan Eichler Program Manager OG SWRO. Hence prior arrangements for restoration to PCSM standards have been made no violations are currently noted; although operator should continue to closely monitor and maintain site and access road until final permanent restoration is achieved as outlined in memo. Department will be notified up commencemnt of final restoration activities. Chevron EHS personnel, Curtis Small, OGI Rick Hoover, and Environmental Trainee Samantha Foulk on site during inspection.
2160134 2013-04-16 No Violations Noted
2189111 2013-07-15 No Violations Noted Multi-well pad. Marcellus. At time of inspection, well 1H drilled, not yet equipped for production. Date of TD was 2/24/2011.

Site ID sign, E&S plan, PPC plan, ESCGP-1 all on-site. Site gated. Access road in good condition. Well site surrounded by chain-link fence to discourage third party access. Pad stabilized, adequately rocked with vegetative growth observed. No accelerated erosion or sedimentation issues observed. Wellhead surrounded by orange security fence. Well tag present, legible. Poly tank on secondary containment, water accumulation noted. Department recommends Operator empty containment as per current regulations.

Spoke to Chevron rep Curtis Small via phone on 7/8/2013 who informed Department that ditch above well site filled in, not needed due to topography, on-site conditions, and vegetative stabilization. At time of inspection, no potential erosion or sedimentation issues were observed as a result of this alteration. Department rep Samantha Foulk field-approved this change to plan.

2248860 2014-02-26 No Violations Noted Multi-well pad. Marcellus. Regulatory inactive status.

RTPT. At time of inspection, well 1H drilled, not yet equipped for production. 2H also drilled, not yet equipped for production. According to records, drilling for 1H occurred 1/28/2011-2/24/2011.

Site ID sign present, in compliance with Act 9 standards. ERP, E&S plan, PPC plan, ESCGP-1, drilling permit all on-site. Site gated. Well site surrounded by fence to discourage third party access.

Wellhead surrounded by gate and orange security fence. Well tag present, legible. Poly tank on secondary containment, sound.

Unable to adequately inspect access road and well site for erosion and sedimentation concerns due to snow-cover. Per previous agreement with Department, restoration activities were scheduled to commence March 30, 2013. A follow-up inspection will be conducted in the spring to ensure site is properly restored.

For data sources see[3]

References