X

Track changes made to this page

If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.



Privacy policy
Close this window

powered by ChangeDetection

Difference between revisions of "37-063-36846"

m
m
Line 3: Line 3:
 
{| class="wikitable welldetails" width="95%"
 
{| class="wikitable welldetails" width="95%"
 
| Well ID: 37-063-36846
 
| Well ID: 37-063-36846
| style="height=100%; align=center" rowspan="14" | {{#display_map: 40.499277, -79.068333 | width=100% | height=100% }}  
+
| style="height=100%; align=center" rowspan="15" | {{#display_map: 40.499277, -79.068333 | width=100% | height=100% }}  
 
|-
 
|-
 
| County: [[Indiana County, Pennsylvania|Indiana]]
 
| County: [[Indiana County, Pennsylvania|Indiana]]
Line 9: Line 9:
 
| Municipality: [[Brush Valley Township, Indiana County, Pennsylvania|Brush Valley Township]]
 
| Municipality: [[Brush Valley Township, Indiana County, Pennsylvania|Brush Valley Township]]
 
|-
 
|-
| Operator Name: [[CHEVRON APPALACHIA LLC|CHEVRON APPALACHIA LLC]]
+
| Operator Name: [[CHEVRON APPALACHIA LLC]]
 
|-
 
|-
| Well Pad ID: [[148232]]
+
| Well Pad ID: [[148232|148232]]
 
|-
 
|-
 
| Farm/Lease Name: DICK 1H
 
| Farm/Lease Name: DICK 1H
Line 25: Line 25:
 
| Horizontal: Yes
 
| Horizontal: Yes
 
|-
 
|-
| Producing: Yes
+
| Well Status: ACTIVE
 
|-
 
|-
| Violations: None
+
| Violations: 0
 
|-
 
|-
 
| Latitude: 40.499277
 
| Latitude: 40.499277
Line 34: Line 34:
 
|-
 
|-
 
|}
 
|}
 +
== Production Data ==
 +
{| class="wikitable sortable" width="95%"
 +
!scope="col" | PERIOD
 +
!scope="col" | GAS QUANTITY
 +
!scope="col" | GAS PRODUCTION DAYS
 +
!scope="col" | CONDENSATE QUANTITY
 +
!scope="col" | CONDENSATE PRODUCTION DAYS
 +
!scope="col" | OIL QUANTITY
 +
!scope="col" | OIL PRODUCTION DAYS
 +
|-
 +
| 2010-3
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
|-
 +
|-
 +
| 2010-2
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
|-
 +
|-
 +
| 2010-2
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
|-
 +
|-
 +
| 2011-1
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
|-
 +
|-
 +
| 2011-2
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
|-
 +
|-
 +
| 2011-2
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
|-
 +
|-
 +
| 2012-1
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
|-
 +
|-
 +
| 2012-2
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
|-
 +
|-
 +
| 2013-1
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
|-
 +
|-
 +
| 2013-2
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
|-
 +
|-
 +
| 2014-1
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
|-
 +
|-
 +
| 2014-2
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
|-
 +
|-
 +
| 2015-02
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
|-
 +
|-
 +
| 2015-01
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
|-
 +
|-
 +
| 2015-03
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
| style="text-align:right;" | 0.0
 +
|-
 +
|}
 +
For data sources see<ref>{{cite web
 +
| title = Oil and Gas Historical Production Report
 +
| publisher = [[Pennsylvania Department of Environmental Protection]]
 +
| date = 2015-05-26
 +
| url = http://wellwiki.org/wiki/Pennsylvania_Oil_and_Gas_Data_Sources#Production
 +
| accessdate = 2015-05-27 }}</ref>
 +
== Waste Data ==
 +
{| class="wikitable sortable" width="95%"
 +
!scope="col" | PERIOD
 +
!scope="col" | TYPE
 +
!scope="col" | QUANTITY
 +
!scope="col" | UNITS
 +
!scope="col" | DISPOSAL METHOD
 +
!scope="col" | WASTE FACILITY PERMIT ID
 +
!scope="col" | WASTE FACILITY NAME
 +
!scope="col" | FACILITY CITY
 +
!scope="col" | FACILITY STATE
 +
|-
 +
| 2011-1
 +
| DRILL CUTTINGS
 +
| style="text-align:right;" | 352.47
 +
| Tons
 +
| LANDFILL
 +
| 100172
 +
| ARDEN LANDFILL
 +
| WASHINGTON
 +
| PA
 +
|-
 +
|}
 +
For data sources see<ref>{{cite web
 +
| title = Oil and Gas Historical Waste Report
 +
| publisher = [[Pennsylvania Department of Environmental Protection]]
 +
| date = 2015-05-26
 +
| url = http://wellwiki.org/wiki/Pennsylvania_Oil_and_Gas_Data_Sources#Waste
 +
| accessdate = 2015-05-26 }}</ref>
 
== Inspection Data ==
 
== Inspection Data ==
 
{| class="wikitable sortable" width="95%"
 
{| class="wikitable sortable" width="95%"
Line 41: Line 221:
 
!scope="col" | COMMENT
 
!scope="col" | COMMENT
 
!scope="col" | VIOLATION ID
 
!scope="col" | VIOLATION ID
 +
!scope="col" | VIOLATION CODE
 +
!scope="col" | VIOLATION_COMMENT
 
|-
 
|-
 
| 1942800
 
| 1942800
Line 46: Line 228:
 
| No Violations Noted
 
| No Violations Noted
 
| Id sign ok. Site constructed. Location staked. No open pits. Site snow covered but no apparent problems.
 
| Id sign ok. Site constructed. Location staked. No open pits. Site snow covered but no apparent problems.
 +
|
 +
|
 
|  
 
|  
 
|-
 
|-
Line 56: Line 240:
 
  Site and access road snow covered at time of inspection, although no obvious signs of accelerated erosion were found leaving access road or well site.  Appeared as though all BMP's were in place in accordance with E&S plan, and were properly maintained.  Minor E&S issue discussed with operator representative Matt Barch, and addressed through compliance assistance in technical inspection of ESCGP-1 plan.  No drill pit constructed on site (closed loop system to be utilized).  No frac pit constructed yet.  No violations found.
 
  Site and access road snow covered at time of inspection, although no obvious signs of accelerated erosion were found leaving access road or well site.  Appeared as though all BMP's were in place in accordance with E&S plan, and were properly maintained.  Minor E&S issue discussed with operator representative Matt Barch, and addressed through compliance assistance in technical inspection of ESCGP-1 plan.  No drill pit constructed on site (closed loop system to be utilized).  No frac pit constructed yet.  No violations found.
  
 +
|
 +
|
 
|  
 
|  
 
|-
 
|-
Line 62: Line 248:
 
| 2011-01-19
 
| 2011-01-19
 
| No Violations Noted
 
| No Violations Noted
 +
|
 +
|
 
|  
 
|  
 
|  
 
|  
Line 69: Line 257:
 
| 2011-01-25
 
| 2011-01-25
 
| No Violations Noted
 
| No Violations Noted
 +
|
 +
|
 
|  
 
|  
 
|  
 
|  
Line 82: Line 272:
 
No signs of any spills or discharges.  No E&S issues found.  No violations found.
 
No signs of any spills or discharges.  No E&S issues found.  No violations found.
  
 +
|
 +
|
 
|  
 
|  
 
|-
 
|-
Line 88: Line 280:
 
| 2011-02-04
 
| 2011-02-04
 
| No Violations Noted
 
| No Violations Noted
 +
|
 +
|
 
|  
 
|  
 
|  
 
|  
Line 95: Line 289:
 
| 2011-02-02
 
| 2011-02-02
 
| No Violations Noted
 
| No Violations Noted
 +
|
 +
|
 
|  
 
|  
 
|  
 
|  
Line 108: Line 304:
 
No violations found.  No signs of any spills or discharges.  No E&S issues found.  No violations found.
 
No violations found.  No signs of any spills or discharges.  No E&S issues found.  No violations found.
  
 +
|
 +
|
 
|  
 
|  
 
|-
 
|-
Line 114: Line 312:
 
| 2011-02-24
 
| 2011-02-24
 
| No Violations Noted
 
| No Violations Noted
 +
|
 +
|
 
|  
 
|  
 
|  
 
|  
Line 130: Line 330:
 
     addressed.  
 
     addressed.  
  
 +
|
 +
|
 
|  
 
|  
 
|-
 
|-
Line 143: Line 345:
 
Minor repairs have been completed to the sediment trap on the far side of the site in response to compliance assistance inspection of 3/2/11.  Site is in compliance.  No E&S issues found.  No violations found.
 
Minor repairs have been completed to the sediment trap on the far side of the site in response to compliance assistance inspection of 3/2/11.  Site is in compliance.  No E&S issues found.  No violations found.
  
 +
|
 +
|
 
|  
 
|  
 
|-
 
|-
Line 157: Line 361:
 
No E&S issues found.  No violations found.  No ev idence of any spills or discharges.
 
No E&S issues found.  No violations found.  No ev idence of any spills or discharges.
  
 +
|
 +
|
 
|  
 
|  
 
|-
 
|-
Line 163: Line 369:
 
| 2011-06-08
 
| 2011-06-08
 
| No Violations Noted
 
| No Violations Noted
 +
|
 +
|
 
|  
 
|  
 
|  
 
|  
Line 170: Line 378:
 
| 2012-03-02
 
| 2012-03-02
 
| No Violations Noted
 
| No Violations Noted
 +
|
 +
|
 
|  
 
|  
 
|  
 
|  
Line 177: Line 387:
 
| 2012-03-02
 
| 2012-03-02
 
| No Violations Noted
 
| No Violations Noted
 +
|
 +
|
 
|  
 
|  
 
|  
 
|  
Line 185: Line 397:
 
| No Violations Noted
 
| No Violations Noted
 
| At the time of inspection, well sign, ES plan, and ESCGP-1 present. Access road stable. Well site gated.  Multi well pad. Site is surrounding by wire fence in order to prevent third party access. Drilling completed 2/24/11. Pad adequately rocked. Wells drilled, not yet fraced nor equipped for production.  Site is temporarily stabilized. No ES concerns noted.  Operator has plans to permanently restore well site March 2013, a letter has been submitted discussing restoration efforts and timeline to Alan Eichler Program Manager OG SWRO.  Hence prior arrangements for restoration to PCSM standards have been made no violations are currently noted; although operator should continue to closely monitor and maintain site and access road until final permanent restoration is achieved as outlined in memo. Department will be notified up commencemnt of final restoration activities. Chevron EHS personnel, Curtis Small, OGI Rick Hoover, and Environmental Trainee Samantha Foulk on site during inspection.
 
| At the time of inspection, well sign, ES plan, and ESCGP-1 present. Access road stable. Well site gated.  Multi well pad. Site is surrounding by wire fence in order to prevent third party access. Drilling completed 2/24/11. Pad adequately rocked. Wells drilled, not yet fraced nor equipped for production.  Site is temporarily stabilized. No ES concerns noted.  Operator has plans to permanently restore well site March 2013, a letter has been submitted discussing restoration efforts and timeline to Alan Eichler Program Manager OG SWRO.  Hence prior arrangements for restoration to PCSM standards have been made no violations are currently noted; although operator should continue to closely monitor and maintain site and access road until final permanent restoration is achieved as outlined in memo. Department will be notified up commencemnt of final restoration activities. Chevron EHS personnel, Curtis Small, OGI Rick Hoover, and Environmental Trainee Samantha Foulk on site during inspection.
 +
|
 +
|
 
|  
 
|  
 
|-
 
|-
|}
 
== Production Data ==
 
{| class="wikitable sortable" width="95%"
 
!scope="col" | PERIOD
 
!scope="col" | GAS QUANTITY
 
!scope="col" | GAS PRODUCTION DAYS
 
!scope="col" | CONDENSATE QUANTITY
 
!scope="col" | CONDENSATE PRODUCTION DAYS
 
!scope="col" | OIL QUANTITY
 
!scope="col" | OIL PRODUCTION DAYS
 
 
|-
 
|-
| 2012-2
+
| 2160134
| style="text-align:right;" | 0.0
+
| 2013-04-16
| style="text-align:right;" | 0.0
+
| No Violations Noted
| style="text-align:right;" | 0.0
+
|  
| style="text-align:right;" | 0.0
+
|  
| style="text-align:right;" | 0.0
+
|  
| style="text-align:right;" | 0.0
+
|  
 
|-
 
|-
 
|-
 
|-
| 2012-1
+
| 2189111
| style="text-align:right;" | 0.0
+
| 2013-07-15
| style="text-align:right;" | 0.0
+
| No Violations Noted
| style="text-align:right;" | 0.0
+
| Multi-well pad. Marcellus. At time of inspection, well 1H drilled, not yet equipped for production. Date of TD was 2/24/2011.  
| style="text-align:right;" | 0.0
+
Site ID sign, E&S plan, PPC plan, ESCGP-1 all on-site. Site gated. Access road in good condition. Well site surrounded by chain-link fence to discourage third party access.
| style="text-align:right;" | 0.0
+
Pad stabilized, adequately rocked with vegetative growth observed. No accelerated erosion or sedimentation issues observed.
| style="text-align:right;" | 0.0
+
Wellhead surrounded by orange security fence. Well tag present, legible.
 +
Poly tank on secondary containment, water accumulation noted. Department recommends Operator empty containment as per current regulations.
 +
 
 +
Spoke to Chevron rep Curtis Small via phone on 7/8/2013 who informed Department that ditch above well site filled in, not needed due to topography, on-site conditions, and vegetative stabilization. At time of inspection, no potential erosion or sedimentation issues were observed as a result of this alteration. Department rep Samantha Foulk field-approved this change to plan.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
| 2011-2
+
| 2248860
| style="text-align:right;" | 0.0
+
| 2014-02-26
| style="text-align:right;" | 0.0
+
| No Violations Noted
| style="text-align:right;" | 0.0
+
| Multi-well pad. Marcellus. Regulatory inactive status.
| style="text-align:right;" | 0.0
+
 
| style="text-align:right;" | 0.0
+
RTPT. At time of inspection, well 1H drilled, not yet equipped for production. 2H also drilled, not yet equipped for production. According to records, drilling for 1H occurred 1/28/2011-2/24/2011.  
| style="text-align:right;" | 0.0
+
|-
+
Site ID sign present, in compliance with Act 9 standards. ERP, E&S plan, PPC plan, ESCGP-1, drilling permit all on-site. Site gated. Well site surrounded by fence to discourage third party access.
|-
+
| 2011-2
+
Wellhead surrounded by gate and orange security fence. Well tag present, legible. Poly tank on secondary containment, sound.
| style="text-align:right;" | 0.0
+
 
| style="text-align:right;" | 0.0
+
Unable to adequately inspect access road and well site for erosion and sedimentation concerns due to snow-cover. Per previous agreement with Department, restoration activities were scheduled to commence March 30, 2013. A follow-up inspection will be conducted in the spring to ensure site is properly restored.
| style="text-align:right;" | 0.0
+
|  
| style="text-align:right;" | 0.0
+
|  
| style="text-align:right;" | 0.0
+
|  
| style="text-align:right;" | 0.0
 
|-
 
|-
 
| 2011-1
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
|-
 
|-
 
| 2010-2
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
|-
 
|-
 
| 2010-3
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
 
|-
 
|-
 
|}
 
|}
== Waste Data ==
+
For data sources see<ref>{{cite web
{| class="wikitable sortable" width="95%"
+
| title = Oil and Gas Historical Inspection Report
!scope="col" | PERIOD
+
| publisher = [[Pennsylvania Department of Environmental Protection]]
!scope="col" | TYPE
+
| date = 2015-05-26
!scope="col" | QUANTITY
+
| url = http://wellwiki.org/wiki/Pennsylvania_Oil_and_Gas_Data_Sources#Inspections
!scope="col" | UNITS
+
| accessdate = 2015-05-27 }}</ref>
!scope="col" | DISPOSAL METHOD
+
== References ==
!scope="col" | WASTE FACILITY PERMIT ID
+
{{reflist}}
!scope="col" | WASTE FACILITY NAME
 
!scope="col" | FACILITY CITY
 
!scope="col" | FACILITY STATE
 
|-
 
| 2011-1
 
| DRILL CUTTINGS
 
| style="text-align:right;" | 352.47
 
| Tons
 
| LANDFILL
 
| 100172
 
| WASTE MANAGEMENT, INC  - ARDEN LANDFILL, INC.
 
| WASHINGTON
 
| PA
 
|-
 
|}
 
==References==
 
{{Reflist}}
 
 
 
 
__NOEDITSECTION__
 
__NOEDITSECTION__
 
[[Category:Wells]]
 
[[Category:Wells]]

Revision as of 11:14, 26 June 2015

Well Details

Well ID: 37-063-36846
Loading map...
County: Indiana
Municipality: Brush Valley Township
Operator Name: CHEVRON APPALACHIA LLC
Well Pad ID: 148232
Farm/Lease Name: DICK 1H
First Permit Date: 2010-04-30
Last Permit Date: 2010-04-30
Spud Date: 2011-01-28
Unconventional: Yes
Horizontal: Yes
Well Status: ACTIVE
Violations: 0
Latitude: 40.499277
Longitude: -79.068333

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS
2010-3 0.0 0.0 0.0 0.0 0.0 0.0
2010-2 0.0 0.0 0.0 0.0 0.0 0.0
2010-2 0.0 0.0 0.0 0.0 0.0 0.0
2011-1 0.0 0.0 0.0 0.0 0.0 0.0
2011-2 0.0 0.0 0.0 0.0 0.0 0.0
2011-2 0.0 0.0 0.0 0.0 0.0 0.0
2012-1 0.0 0.0 0.0 0.0 0.0 0.0
2012-2 0.0 0.0 0.0 0.0 0.0 0.0
2013-1 0.0 0.0 0.0 0.0 0.0 0.0
2013-2 0.0 0.0 0.0 0.0 0.0 0.0
2014-1 0.0 0.0 0.0 0.0 0.0 0.0
2014-2 0.0 0.0 0.0 0.0 0.0 0.0
2015-02 0.0 0.0 0.0 0.0 0.0 0.0
2015-01 0.0 0.0 0.0 0.0 0.0 0.0
2015-03 0.0 0.0 0.0 0.0 0.0 0.0

For data sources see[1]

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE
2011-1 DRILL CUTTINGS 352.47 Tons LANDFILL 100172 ARDEN LANDFILL WASHINGTON PA

For data sources see[2]

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID VIOLATION CODE VIOLATION_COMMENT
1942800 2011-01-14 No Violations Noted Id sign ok. Site constructed. Location staked. No open pits. Site snow covered but no apparent problems.
1944402 2011-01-20 No Violations Noted Marcellus well. Conductor pipe set. Site ID sign in place. E&S plan on site. Setting up drilling equipment at time of inspection.

Approved ESCGP-1 permit on site. Technical review of ESCGP-1 completed.

Site and access road snow covered at time of inspection, although no obvious signs of accelerated erosion were found leaving access road or well site.  Appeared as though all BMP's were in place in accordance with E&S plan, and were properly maintained.  Minor E&S issue discussed with operator representative Matt Barch, and addressed through compliance assistance in technical inspection of ESCGP-1 plan.  No drill pit constructed on site (closed loop system to be utilized).  No frac pit constructed yet.  No violations found.
1944598 2011-01-19 No Violations Noted
1946175 2011-01-25 No Violations Noted
1947172 2011-01-28 No Violations Noted Marcellus well. Conductor pipe set. Site ID sign in place. E&S plan on site. Drilling rig in place.

Approved ESCGP-1 permit on site. Technical review of ESCGP-1 completed.

Site and access road snow covered at time of inspection, although no obvious signs of accelerated erosion were found leaving access road or well site.  Appeared as though all BMP's were in place in accordance with E&S plan, and were properly maintained.

No drill pit constructed on site (closed loop system to be utilized). No frac pit constructed yet. No violations found. No signs of any spills or discharges. No E&S issues found. No violations found.

1947871 2011-02-04 No Violations Noted
1947880 2011-02-02 No Violations Noted
1950400 2011-02-15 No Violations Noted Marcellus well. Site ID sign in place. E&S plan on site. BJ service company on site for cementing.

Approved ESCGP-1 permit on site. Technical review of ESCGP-1 completed.

Site and access road snow covered at time of inspection, although no obvious signs of accelerated erosion were found leaving access road or well site.  Appeared as though all BMP's were in place in accordance with E&S plan, and were properly maintained.

Drill cuttings and fluids being contained in above ground tanks (closed loop system being used). No frac pit constructed. No violations found. No signs of any spills or discharges. No E&S issues found. No violations found.

1953155 2011-02-24 No Violations Noted
1955295 2011-03-02 No Violations Noted Marcellus well. Site ID sign in place. E&S plan on site. Drilling taking place at time of inspection.

Approved ESCGP-1 permit on site. Technical review of ESCGP-1 completed. Drill cuttings and fluids being contained in above ground tanks (closed loop system being used). No frac pit constructed. Access road was stabilized with rock. Rock installed in all ditch lines, and culvert outlets. No signs of accelerated erosion on roadway. BMP's installed on site in accordance with E&S plan.

  • Some minor repairs are needed to the BMP's, in particular to the sediment trap on the far side of the site. This was discussed with on-site
   company representative Don Henson, as well as company rep Matt Barch.  Both indicated the concerns would be immediately 
   addressed. 
1956869 2011-03-09 No Violations Noted Marcellus well. Site ID sign in place. E&S plan on site. Drilling completed, currently drilling second well on same pad.

Approved ESCGP-1 permit on site. Technical review of ESCGP-1 completed. Access road was stabilized with rock. Rock installed in all ditch lines, and culvert outlets. No signs of accelerated erosion on roadway. BMP's installed on site in accordance with E&S plan, and adequately maintained. Site is stabilized with rock. Perimeter of site seeded/mulched, and erosion blankets installed. Minor repairs have been completed to the sediment trap on the far side of the site in response to compliance assistance inspection of 3/2/11. Site is in compliance. No E&S issues found. No violations found.

1965133 2011-03-25 No Violations Noted Marcellus well. Site ID sign in place. E&S plan on site. Drilling recently completed. Not equipped for production.

Approved ESCGP-1 permit on site. Technical review of ESCGP-1 completed. Access road was stabilized with rock. Rock installed in all ditch lines, and culvert outlets. No signs of accelerated erosion on roadway. BMP's installed on site in accordance with E&S plan, and adequately maintained. Site is stabilized with rock. Perimeter of site seeded/mulched, and erosion blankets installed. No impoundments/pits on site. No E&S issues found. No violations found. No ev idence of any spills or discharges.

1979929 2011-06-08 No Violations Noted
2047593 2012-03-02 No Violations Noted
2121806 2012-03-02 No Violations Noted
2126972 2012-12-06 No Violations Noted At the time of inspection, well sign, ES plan, and ESCGP-1 present. Access road stable. Well site gated. Multi well pad. Site is surrounding by wire fence in order to prevent third party access. Drilling completed 2/24/11. Pad adequately rocked. Wells drilled, not yet fraced nor equipped for production. Site is temporarily stabilized. No ES concerns noted. Operator has plans to permanently restore well site March 2013, a letter has been submitted discussing restoration efforts and timeline to Alan Eichler Program Manager OG SWRO. Hence prior arrangements for restoration to PCSM standards have been made no violations are currently noted; although operator should continue to closely monitor and maintain site and access road until final permanent restoration is achieved as outlined in memo. Department will be notified up commencemnt of final restoration activities. Chevron EHS personnel, Curtis Small, OGI Rick Hoover, and Environmental Trainee Samantha Foulk on site during inspection.
2160134 2013-04-16 No Violations Noted
2189111 2013-07-15 No Violations Noted Multi-well pad. Marcellus. At time of inspection, well 1H drilled, not yet equipped for production. Date of TD was 2/24/2011.

Site ID sign, E&S plan, PPC plan, ESCGP-1 all on-site. Site gated. Access road in good condition. Well site surrounded by chain-link fence to discourage third party access. Pad stabilized, adequately rocked with vegetative growth observed. No accelerated erosion or sedimentation issues observed. Wellhead surrounded by orange security fence. Well tag present, legible. Poly tank on secondary containment, water accumulation noted. Department recommends Operator empty containment as per current regulations.

Spoke to Chevron rep Curtis Small via phone on 7/8/2013 who informed Department that ditch above well site filled in, not needed due to topography, on-site conditions, and vegetative stabilization. At time of inspection, no potential erosion or sedimentation issues were observed as a result of this alteration. Department rep Samantha Foulk field-approved this change to plan.

2248860 2014-02-26 No Violations Noted Multi-well pad. Marcellus. Regulatory inactive status.

RTPT. At time of inspection, well 1H drilled, not yet equipped for production. 2H also drilled, not yet equipped for production. According to records, drilling for 1H occurred 1/28/2011-2/24/2011.

Site ID sign present, in compliance with Act 9 standards. ERP, E&S plan, PPC plan, ESCGP-1, drilling permit all on-site. Site gated. Well site surrounded by fence to discourage third party access.

Wellhead surrounded by gate and orange security fence. Well tag present, legible. Poly tank on secondary containment, sound.

Unable to adequately inspect access road and well site for erosion and sedimentation concerns due to snow-cover. Per previous agreement with Department, restoration activities were scheduled to commence March 30, 2013. A follow-up inspection will be conducted in the spring to ensure site is properly restored.

For data sources see[3]

References