Well Details

Well ID: 37-063-36247
Loading map...
Operator Name: PENN VIEW EXPLORATION CORP
First Permit Date: 2008-09-30
Last Permit Date: 2008-09-30
Spud Date: 2009-01-27
Unconventional: No
Horizontal: No
Violations: 3
Latitude: 40.440107
Longitude: -79.091516

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS
2013-0 13094.0 365.0 0.0 0.0 0.0 0.0
2012-0 12647.0 365.0 0.0 0.0 0.0 0.0
2011-0 9642.4 365.0 0.0 0.0 0.0 0.0
2010-0 12868.0 307.0 0.0 0.0 0.0 0.0
2008-0 0.0 0.0 0.0 0.0 0.0 0.0

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE
2012-0 PRODUCED FLUID 75.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095273 PA BRINE TRT INC - JOSEPHINE PLT, INDIANA COUNTY JOSEPHINE PA
2012-0 PRODUCED FLUID 75.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095273 PA BRINE TRT INC - JOSEPHINE PLT, INDIANA COUNTY JOSEPHINE PA
2013-0 PRODUCED FLUID 85.0 Bbl CENT WASTE TRT FAC NPDES DISCHARGE PA0095273 FLUID RECOVERY SERVICE JOSEPHINE FACILITY JOSEPHINE PA

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID
1735737 2008-09-11 No Violations Noted well staked - site not made/waiver ok
1768266 2009-01-29 No Violations Noted Drilling 12 1/4" 330' Pit & E&S OK
1781766 2009-02-09 Violation(s) Noted Drilling had been completed at the time of the inspection. The well was not equipped for production. The following deficiencies were found at this site: 1- The site was not constructed according to the E&S plan that was on-site. Because this site has a waiver, the approved E&S plan should be followed and any changes should be discussed with the Department prior to implementation.

2- The grub/brush line was installed on the wrong side of the silt fence. 3- There were several instances of failing filter fence. 4- The access road could use additional BMP¿s to limit the amount of sediment entering the stream. 5- The pit installation that was observed at the site could cause undue stress to the integrity of the pit liner and could lead to a tear.

560056
1781766 2009-02-09 Violation(s) Noted Drilling had been completed at the time of the inspection. The well was not equipped for production. The following deficiencies were found at this site: 1- The site was not constructed according to the E&S plan that was on-site. Because this site has a waiver, the approved E&S plan should be followed and any changes should be discussed with the Department prior to implementation.

2- The grub/brush line was installed on the wrong side of the silt fence. 3- There were several instances of failing filter fence. 4- The access road could use additional BMP¿s to limit the amount of sediment entering the stream. 5- The pit installation that was observed at the site could cause undue stress to the integrity of the pit liner and could lead to a tear.

560056
1781766 2009-02-09 Violation(s) Noted Drilling had been completed at the time of the inspection. The well was not equipped for production. The following deficiencies were found at this site: 1- The site was not constructed according to the E&S plan that was on-site. Because this site has a waiver, the approved E&S plan should be followed and any changes should be discussed with the Department prior to implementation.

2- The grub/brush line was installed on the wrong side of the silt fence. 3- There were several instances of failing filter fence. 4- The access road could use additional BMP¿s to limit the amount of sediment entering the stream. 5- The pit installation that was observed at the site could cause undue stress to the integrity of the pit liner and could lead to a tear.

560068
1781766 2009-02-09 Violation(s) Noted Drilling had been completed at the time of the inspection. The well was not equipped for production. The following deficiencies were found at this site: 1- The site was not constructed according to the E&S plan that was on-site. Because this site has a waiver, the approved E&S plan should be followed and any changes should be discussed with the Department prior to implementation.

2- The grub/brush line was installed on the wrong side of the silt fence. 3- There were several instances of failing filter fence. 4- The access road could use additional BMP¿s to limit the amount of sediment entering the stream. 5- The pit installation that was observed at the site could cause undue stress to the integrity of the pit liner and could lead to a tear.

560068
1781766 2009-02-09 Violation(s) Noted Drilling had been completed at the time of the inspection. The well was not equipped for production. The following deficiencies were found at this site: 1- The site was not constructed according to the E&S plan that was on-site. Because this site has a waiver, the approved E&S plan should be followed and any changes should be discussed with the Department prior to implementation.

2- The grub/brush line was installed on the wrong side of the silt fence. 3- There were several instances of failing filter fence. 4- The access road could use additional BMP¿s to limit the amount of sediment entering the stream. 5- The pit installation that was observed at the site could cause undue stress to the integrity of the pit liner and could lead to a tear.

560069
1781766 2009-02-09 Violation(s) Noted Drilling had been completed at the time of the inspection. The well was not equipped for production. The following deficiencies were found at this site: 1- The site was not constructed according to the E&S plan that was on-site. Because this site has a waiver, the approved E&S plan should be followed and any changes should be discussed with the Department prior to implementation.

2- The grub/brush line was installed on the wrong side of the silt fence. 3- There were several instances of failing filter fence. 4- The access road could use additional BMP¿s to limit the amount of sediment entering the stream. 5- The pit installation that was observed at the site could cause undue stress to the integrity of the pit liner and could lead to a tear.

560069
1781836 2009-04-06 No Violations Noted This inspection was performed as a Compliance Evaluation to a NOV that was issued on 2/9/09.

3/2/09- Written response was received from the operator. 4/6/09- Jarrod Shultz performed an inspection of the well site. The well site was equipped for production. The E&S plan has been revised to include any changes from the original plan. The filter fence has been repaired and/or replaced where it was needed. Additional E&S controls (silt fence, hay bales, and seeding & mulching) were added to the access road to assist in controlling Erosion and Sedimentation. With proper maintenance, the current E&S controls should properly limit erosion and sedimentation of the site and access road.

1817415 2009-07-31 No Violations Noted According to records, well completed on 2/5/09 to a depth of 5,037 ft and WRAC submitted on 4/28/09. Active permit since 9/30/09. Well head completed with 7¿ pipe reduced to 4¿ and reduced to 2¿ production line with 3 shut off valves. Production equipment consisted of heater, separator, data logger and 100 bbl tank. Line pressure on separator at 125 psi. No E&S issues and no IW issues during inspection surrounding the production well. The main access road to well will require additional E&S activity. Discussed topic with Penn View, Rick Blazek.
1817964 2009-08-03 No Violations Noted Drilling was completed on 2/5/2009. There are on E&S issues on the site at the time of inspection. Brine tank is in sound condition. Well is in production and site is restored. There is approximately 95% perrenial vegetative cover at the well site.
1965291 2011-04-13 No Violations Noted At the time of inspection, well drilled and in production. Well completed on 02/05/09. Well tag present. Site adequately and uniformly restored with >70% vegetative cover. Brine tank appears sound. No accelerated ES issues or IW issues noted on site.

Minor ES issues noted along shared access road due to new construction of Krause 1 site (Spud called for 3/30/11), which are addressed accordingly in Krause 1 site inspection; therefore operator should continue maintain shared access road accordingly.

2154420 2013-04-02 Indiana West Wheatfield Twp No Violations Noted