37-003-22169

Well Details

Well ID: 37-003-22169
Loading map...
Country: United States
State: Pennsylvania
County: Allegheny
Municipality: Ohio Township
Operator Name: AMER NATURAL RESOURCES LLC
Well Pad ID:
Farm/Lease Name: CHARLES LENZNER UNIT
License Status:
Spud Date:
Permit Date: 2011-03-14
Well Type: OIL
Unconventional Well: N
Configuration: Vertical Well
Conservation: No
Latitude: 40.535906
Longitude: -80.115725

For data sources see[1][2][3]

Well History

Date Event
2011-03-14 New Permit Application
2011-04-22 Performed Spud Operation
2014-08-25 Begin Plugging
2014-08-28 Finished Plugging

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2011 AMER NATURAL RESOURCES LLC 0.00 0 0.00 0 0.00 0
2012 AMER NATURAL RESOURCES LLC 0.00 0 0.00 0 0.00 0
2013 AMER NATURAL RESOURCES LLC 0.00 0 0.00 0 0.00 0
2014 AMER NATURAL RESOURCES LLC 0.00 0 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2011 AMER NATURAL RESOURCES LLC Drilling Fluid Waste 80.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095273
2012 AMER NATURAL RESOURCES LLC Drilling Fluid Waste 110.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095273

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
1974603 Primary Facility 2011-04-27 Drilling/Alteration No Violations Noted 6 BBL ON 95/8" CEMENT.
1976504 Primary Facility 2011-04-25 Drilling/Alteration No Violations Noted DRILLING JUST STARTING. NO CASING IN THE GROUND.
1983162 Primary Facility 2011-05-12 Drilling/Alteration No Violations Noted DRILLING COMPLETE. EQUIPTMENT GONE.
1983734 Primary Facility 2011-04-20 Routine/Complete Inspection No Violations Noted On April 20th, 2011 I conducted a routine inspection of the above site. Drilling has not yet started. A site ID sign and E&S plan were posted at the site. The access road could use some additional rock. Access was through Unit #2 and #4. All E&S controls were in place and constructed according to the plan at site. Pit was constructed. No accelerated erosion was observed at the time of inspection. The slopes were mulched. The operator should continue to inspect the E&S controls until the site is restored and 70% vegetative cover is achieved.
1983831 Primary Facility 2011-05-12 Routine/Complete Inspection No Violations Noted On May 12th, 2011 I conducted a routine inspection of the above site. Drilling was completed. A site ID sign and E&S plan were posted at the site. The access road was in fair condition. Access was through Unit #2 and #4. Pit was appeared to be in good condition and still contained fluids. No accelerated erosion was observed at the time of inspection. The operator should continue to inspect the E&S controls until the site is restored and 70% vegetative cover is achieved.
2018480 Primary Facility 2011-10-05 Drilling/Alteration No Violations Noted THE PIT IS OPEN. WELL WAS NEVER COMPLETED. NO ACTIVITY SINCE MAY 2011.
2051751 Primary Facility 2012-03-20 Administrative/File Review No Violations Noted On December 5, 2012, the Department received a request for a six-month extension for the reclamation of American Natural Resources’ (ANR) Charles Lenzer Unit #3. The well reached total depth on4/29/11 and restoration should have been done by1/29/12.
2065243 Primary Facility 2012-04-03 Routine/Complete Inspection No Violations Noted JACK IS HOOKED UP. SITE IS RESTORED.
2086085 Primary Facility 2012-07-24 Routine/Complete Inspection No Violations Noted On March 15, 2012, the Department granted American Natural Resources (ANR) a six-month extension on the reclamation of their Charles Lenzner #3 site. The new reclamation date is July 29, 2012.
2100553 Primary Facility 2012-09-06 Routine/Complete Inspection No Violations Noted On September 6, 2012, WQS John Ley and I stopped at ANR’s’, Charles Lenzner #3 site to check the restoration progress. The site is in fair shape. Overall the it is vegetated but the silt fence is still up. We also did not see signs on the well itself.
2247383 Primary Facility 2014-01-22 Routine/Complete Inspection No Violations Noted WELL WAS DRILLED BUT NOT PRODUCED.
2296851 Primary Facility 2014-08-04 Plugging(Includes Plugged/Mined Through) No Violations Noted THIS OIL AND GAS WELL WAS NOT PRODUCTIVE. THE JACK HAS BEEN REMOVED. THE RODS AND TUBING ARE STILL IN THE WELL. THE WELL WILL BE PLUGGED.
2303927 Primary Facility 2014-08-25 Plugging(Includes Plugged/Mined Through) No Violations Noted RIG IS SETTING UP TO PULL RODS AND TUBING. TUBING WILL BE RUN BACK IN TO SET PLUGS.
2303928 Primary Facility 2014-08-28 Plugging(Includes Plugged/Mined Through) No Violations Noted APPALACHIAN WELL SERVICES IS SETTING UP TO CEMENT THE FINAL PLUG IN THIS WELL.
2303930 Primary Facility 2014-09-02 Plugging(Includes Plugged/Mined Through) No Violations Noted THIS WELL IS PLUGGED. THE MARKER IS NOT YET WELDED TO THE CASING.
2307463 Primary Facility 2014-09-15 Plugging(Includes Plugged/Mined Through) No Violations Noted A PERMENENT MARKER HAS BEEN WELDED TO THIS PLUGGED WELL.
2728004 Primary Facility 2018-05-04 Routine/Complete Inspection No Violations Noted Well plugged monument installed

For data sources see[7]