1179788941
|
2007-05-21
|
|
On site to witness testing of BOP,operator closed BOP and pressured up to 500 psi and attempted to test first test failed due to faulty flange gasket,second attempt passed after operator changed seal ring and renippled up BOP no leaks detected after new seal ring installed.
|
|
|
|
1288703869
|
2010-11-02
|
|
On day of inspection well is supplied with a rabbet and 7cas,4.5cas,1.5tubing.There is a 100bbl tank with dike, id and all carbon filters inplace.Preliminary restoration passed.
|
|
|
|
17587135
|
2011-10-31
|
|
On day of inspection well was complete with plunger lift system. Tank battery contents included one 110 barrel oil storage tank and a mechanical separator. Site met requirements of the ORC and preliminary restoration is now passed.
|
|
|
|
2147433744
|
2012-07-16
|
|
Inspection of the well head found the following equipment present, 4.5production casing, 1.5 tubing with the commercial production valves closed and the domestic valves open, the well being produced by the means of a plunger lift system . A single 100 barrel tank along with a separator and gas meter are present in an established containment dike with proper well identification present.
|
|
|
|