{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":40.101536,"lon":-80.126369,"icon":""}]} |
Country: United States | |
State: Pennsylvania | |
County: Washington | |
Municipality: North Bethlehem Township | |
Operator Name: RICE DRILLING B LLC | |
Well Pad ID: | |
Farm/Lease Name: IRON MAN 12H | |
License Status: | |
Spud Date: | |
Permit Date: 2013-11-20 | |
Well Type: GAS | |
Unconventional Well: Y | |
Configuration: Horizontal Well | |
Conservation: No | |
Latitude: 40.101536 | |
Longitude: -80.126369 |
Date | Event |
---|---|
2013-11-20 | New Permit Application |
For data sources see[4]
Inspection ID | Inspection Category | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|---|
2444781 | Primary Facility | 2016-01-27 | Incident- Response to Accident or Event | No Violations Noted | On 1/27/16, I performed an incident inspection at the Ironman Pad in response to these concerns and identified violations including the following:
•My Inspection indicates that either portions of the initial slide or a new slide are currently outside the LOD and within a stream bed directly impacting an operator delineated stream. •A sump outlet shown in the plans extending south east from the southern corner of the pad had a pipe extension added conducting it an additional ~50 feet to a CFS dam not shown or redlined on site plans. Water was running under the CFS dam still carrying sediment and then continuing around perimeter CFS, out of the LOD and into the adjacent stream channel. •In the area where the LOD extends along a spur line NW of the pad a number of hay bales and sections of silt sock have been added in an operator delineated intermittent stream. •An erosion channel was found extending from the north side of the pad near the spur line into the intermittent stream bed. -->Further details in fu |
2527002 | Primary Facility | 2016-03-08 | Follow-up Inspection | Outstanding Violations - No Viols Req'd | On 3/8/16, I performed a follow up inspection at the Iron Man Pad regarding an NOV from 1/27/16 (enforcement ID: 333960/Inspection ID: 2444782) accompanied by DEP Engineer Emmanuel Nwaobilo and made the following observations:
•While the pipe extension from the sump outlet noted in the previous extension was removed and additional sections of sock and erosion matting has been added erosion damage outside the LOD and pollution to the Waters of the Commonwealth appears to be ongoing. This constitutes a continuation of the violations of 35 P.S. § 691.401, 78.53, 102.4(B)1, and 102.11(A)1 noted in the inspection from 1/27/16 by continuing in failing to design, implement, and maintain the site E&S BMP’s in such a manner that it prevents and minimizes erosion and sedimentation resulting in a discharge of sediment to Waters of the Commonwealth. •Erosion control measures and stabilization around the landslide that crossed the site LOD have been modified, however no observable effort has been made to remediate the |
2527354 | Primary Facility | 2016-06-28 | Follow-up Inspection | No Violations Noted | On 6/28/16 I performed a follow up inspection of the Iron Man site accompanied by DEP WQS John Parry and Rice representative Jonathan Davis in response to violations noted during inspections on 1/27/16 (ID: 2444782) and 3/8/16 (ID: 2527004) and made the following observations:
•The land slide located along the site LOD on the south eastern border of the site remained unremediated at the time of inspection and continues to impact the Waters of the Commonwealth. This constitutes a continuation of the violations of 35 P.S. § 691.401, 78.53, 102.4(B)1, and 102.11(A)1 noted in the inspection from 1/27/16 by continuing in failing to design, implement, and maintain the site E&S BMP’s in such a manner that it prevents and minimizes erosion and sedimentation resulting in a discharge of sediment to Waters of the Commonwealth. •The area within the site LOD directly up gradient of the slide may be showing additional ground movement but significant disturbance of the area by cattle made definitive assessment unfeasible |
2527836 | Primary Facility | 2016-09-30 | Routine/Partial Inspection | No Violations Noted | Routine/Partial inspection conducted to assess an ongoing issue at the site. |