{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":40.514333,"lon":-79.706388,"icon":""}]} |
County: Allegheny | |
Municipality: Plum Borough | |
Operator Name: PENNECO OIL CO INC | |
First Permit Date: 2011-05-16 | |
Last Permit Date: 2011-05-16 | |
Spud Date: 2011-06-13 | |
Unconventional: No | |
Horizontal: Yes | |
Violations: None | |
Latitude: 40.514333 | |
Longitude: -79.706388 |
INSPECTION ID | DATE | DESCRIPTION | COMMENT | VIOLATION ID |
---|---|---|---|---|
1983213 | 2011-06-08 | No Violations Noted | PAD BUILT FOR A SHALLOW HORIZONTAL OIL WELL.
ACCESS AND E&S OK. |
|
1983776 | 2011-06-14 | No Violations Noted | CONDUCTOR IN AND CEMENTED IN THIS HORIZONTAL OIL WELL. | |
1983786 | 2011-06-16 | No Violations Noted | RIG DOWN FOR REPAIRS. SITE, PIT, E&S, AND ACCESS, OK. | |
1983787 | 2011-06-24 | No Violations Noted | RUNNING RODS TO RESUME DRILLING.
SITE, PIT, E&S, AND ACCESS, OK. |
|
1983788 | 2011-06-28 | No Violations Noted | TD OF 7 7/8" HOLE IS 3392'. BIGGER RIG WILL MOVE IN ON 7/7/11. | |
1983789 | 2011-06-15 | No Violations Noted | RIG IDLE. PROBLEMS WIT THREADS ON CASING. | |
1985337 | 2011-06-08 | No Violations Noted | On June 8th , 2011 I conducted a routine inspection of the above site. The site was under construction but almost complete. The access road was in good condition. A Site ID and E&S plan were posted at the site. E&S controls were in place. The pit was constructed. The operator should continue to inspect the E&S controls until site restoration is complete. | |
1986504 | 2011-06-14 | No Violations Noted | On June 14th , 2011 I conducted a routine inspection of the above site. The rig was set up on site. The access road was in good condition. A Site ID and E&S plan were posted at the site. E&S controls were in place. The pit was constructed. The operator should continue to inspect the E&S controls until site restoration is complete. No spills, leaks, or accelerated erosion were observed at the time of inspection. | |
1986608 | 2011-06-24 | No Violations Noted | On June 24th , 2011 I conducted a routine inspection of the above site. Drilling had started. The access road was in good condition. A Site ID and E&S plan were posted at the site. Water trucks were on site. E&S controls were in place. The pit appeared to be in good condition. The operator should continue to inspect the E&S controls until site restoration is complete. No spills, leaks, or accelerated erosion were observed at the time of inspection. | |
1991678 | 2011-07-06 | No Violations Noted | US ENERGY BIG RIG IS IN BUT NOT YET DRILLING THIS HORIZONTAL OIL AND GAS WELL.
KICK PLUG CEMENTED BACK TO 2492'. |
|
1992021 | 2011-07-06 | No Violations Noted | On July 6th , 2011 I conducted a routine inspection of the above site. Drilling had started. The access road was in good condition. A Site ID and E&S plan were posted at the site. The next/bigger rig had moved in. E&S controls were in place. The pit appeared to be in good condition. The operator should continue to inspect the E&S controls until site restoration is complete. No spills, leaks, or accelerated erosion were observed at the time of inspection. | |
1993478 | 2011-07-26 | No Violations Noted | On July 26th , 2011 I conducted a routine inspection of the above site in response to a noise complaint. Drilling was occurring. The access road was in good condition. A Site ID and E&S plan were posted at the site. 12 frac tanks were at the site. E&S controls were in place. The pit appeared to be in good condition. A small slip was developing on the fill slope. Crews were on site to make repairs. The operator should continue to inspect the E&S controls until site restoration is complete. No spills, leaks, or accelerated erosion were observed at the time of inspection. | |
1993497 | 2011-08-03 | No Violations Noted | On August 3rd , 2011 I conducted a routine inspection of the above site. Drilling was completed and the rig was tearing down. The access road was in good condition. A Site ID and E&S plan were posted at the site. E&S controls were in place. The pit appeared to be in good condition. The silt sock required maintenance. The operator was contacted. The operator should continue to inspect the E&S controls until site restoration is complete. No spills, leaks, or accelerated erosion were observed at the time of inspection. | |
1993503 | 2011-08-04 | No Violations Noted | On August 4th , 2011 I conducted a follow up inspection of the above site to check on repairs made to the silt sock surrounding the site. The necessary repairs had been completed. The rig had moved offsite. The access road was in good condition. A Site ID and E&S plan were posted at the site. E&S controls were in place. The pits appeared to be in good condition. Crews were cleaning the mud tanks. The operator should continue to inspect the E&S controls until site restoration is complete. No spills, leaks, or accelerated erosion were observed at the time of inspection. | |
1993798 | 2011-07-26 | No Violations Noted | RIG WORKING TO GET CORRECT ANGLE TO DRILL HORIZONTALLY IN THE SPEECHLY FORMATION. | |
1993803 | 2011-07-18 | No Violations Noted | HORIZONTAL OIL AND GAS WELL. TOP OF KOP IS 2492'. DRILLING 300' INTO CURVE. | |
1993812 | 2011-07-13 | No Violations Noted | HORIZONTAL OIL AND GAS WELL DRILLING AT 2600'. KOP IS 2492' | |
1998345 | 2011-08-03 | No Violations Noted | DRILLING COMPLETE AND THE RIG IS GONE.
SITE, PIT, E&S, AND ACCESS, IS OK. |
|
1998347 | 2011-08-05 | No Violations Noted | THIS IS A HORIZONTAL OIL AND GAS WELL. THE RIG IS GONE.
FRACK TANKS ARE SET AND A NEW PIT HAS BEEN DUG. THE SITE IS CLEAN AND DOZED. |
|
2001758 | 2011-08-16 | No Violations Noted | HORIZONTAL OIL WELL.
SERVICE RIG SET UP RUNNING PIPE. THE WELL WILL BE FRACED ON 8/18/11. SITE, PIT,, E&S, AND ACCESS GOOD. |
|
2001797 | 2011-08-29 | No Violations Noted | RUNNING TUBING TO PUMP AIR TO CLEAN HOLE. | |
2001799 | 2011-08-24 | No Violations Noted | WELL IS COMPLETE AND FRACED. AFLARE STACK HAS BEEN SET, BUT IS NOT BURNING. | |
2035041 | 2012-01-04 | No Violations Noted | HORIZONTAL OIL WELL IS HOOKED UP. ANULUS IS OPEN. SITE IS RESTORED. | |
2054231 | 2012-02-22 | No Violations Noted | THIS IS A PRODUCING HORIZONTAL OIL AND GAS WELL.
THE SITE IS RESTORED. |
|
2106083 | 2012-10-04 | No Violations Noted | John Ley WQS SWRO, was on site to complete a routine inspection. The well was equipped for production. Brine tank located onsite appeared to be in sound condition. There was no observed accelerated erosion or sedimentation in on the access road or well-site. The site had at least 70% vegetation on the hillsides. |
PERIOD | GAS QUANTITY | GAS PRODUCTION DAYS | CONDENSATE QUANTITY | CONDENSATE PRODUCTION DAYS | OIL QUANTITY | OIL PRODUCTION DAYS |
---|---|---|---|---|---|---|
2012-0 | 20871.0 | 366.0 | 0.0 | 0.0 | 117.86 | 366.0 |
2011-0 | 7897.0 | 92.0 | 0.0 | 0.0 | 130.2 | 92.0 |
PERIOD | TYPE | QUANTITY | UNITS | DISPOSAL METHOD | WASTE FACILITY PERMIT ID | WASTE FACILITY NAME | FACILITY CITY | FACILITY STATE |
---|---|---|---|---|---|---|---|---|
2012-0 | PRODUCED FLUID | 356.0 | Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0101508 | PA BRINE TRT INC - FRANKLIN PLT - VENANGO CO | FRANKLIN | PA |
2011-0 | DRILLING FLUID WASTE | 330.0 | Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0095443 | HART RESOURCE TECHNOLOGIES, INC. - CREEKSIDE | CREEKSIDE | PA |
2011-0 | DRILLING FLUID WASTE | 960.0 | Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0101508 | PA BRINE TRT INC - FRANKLIN PLT - VENANGO CO | FRANKLIN | PA |
2011-0 | FRACING FLUID WASTE | 2450.0 | Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0101508 | PA BRINE TRT INC - FRANKLIN PLT - VENANGO CO | FRANKLIN | PA |
2011-0 | PRODUCED FLUID | 160.0 | Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0101508 | PA BRINE TRT INC - FRANKLIN PLT - VENANGO CO | FRANKLIN | PA |
2011-0 | DRILLING FLUID WASTE | 1890.0 | Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0091472 | TUNNELTON LIQUIDS COMPANY | SALTSBURG | PA |